|
Bulletin: SVB-116
Date Issued: January 24, 2006
Category: Design Improvements
Subject: Inverter Structural Design Correction
Machine Models: High-Speed Top Feeders
Back to Index
Problem:
One of our
customers reported experiencing a significant structural failure of
the welded joint assembly on the operator side of the machine where
the inverter pivot shaft assembly mates to the inverter frame. See
photos below. The sagging inverter assembly on the operator side
also caused weld cracking to occur on the drive side of the machine
where the stub axle is attached to the inverter frame.
This damage
rendered the inverter assembly of the HSTF inoperative until a
temporary weld repair was performed. This HSTF had been in service
approximately 3 months prior to this event.
 

In response to
this report, Alliance has redesigned the structural mounting of the
inverter shaft assembly to the inverter frame on both the drive and
operator sides. This change is now effective for all new production
HSTFs.
For in-service
HSTFs Alliance has developed a preventative modification to this
welded joint. Four gussets are added to the joint on the
operator side of the machine. Rework is also required on the
drive side of the machine. The retrofit modification provides
improved design strength and is structurally equivalent to the
revised production configuration.
Back to top
Recommended
action:
Alliance
strongly recommends that maintenance personnel immediately visually
inspect the inverter assembly for the presence of any cracks or
damage in the areas shown below on the ends of the inverter
assembly. This photograph shows the operator side of the inverter in
the pre-modified configuration. Inspect this area on both the drive
and operator sides of the inverter frame.
|

Inspect for cracks around the
periphery of this torque tube where it mates with the
inverter frame assembly. |
-
If any
cracks are found, do not operate the HSTF and contact Alliance
immediately for further guidance prior to attempting any
repairs. Depending on their size, cracks in the welds themselves
can possibly be ground out and rewelded as a temporary repair.
However, if cracks are found in the base material a technical
evaluation by Alliance Engineering is required prior to
proceeding further with any repairs.
-
If no cracks
are found, Alliance strongly recommends that you perform the
preventative modification described below
on each
affected machine
within 30
days after receipt of this service bulletin. The parts kit
required to accomplish this modification will be provided under
warranty at no charge to operators of the affected machines.
This
modification must be performed by a certified welder.
The modification procedure is anticipated to require up to 8 hours
of elapsed downtime to complete, and Alliance will reimburse for
labor charges incurred for the welding.
-
If an
in-house certified welder is available submit an invoice to
Alliance Field Service for the welding labor charges after the
repair is completed.
-
If an
outside certified welder must be contracted, please obtain an
estimate for welding labor charges and send to Alliance Field
Service for a review prior to proceeding.
The parts kit to
accomplish this modification consists of four steel gussets and 6
longer bolts with washers. The parts kit and repair drawings will be
shipped by the end of January.>
If you need
additional assistance to perform this modification, please call Mr.
Gary Kneale of Alliance Field Service at: (509) 842-5134.
Back to top
Modification
Procedure:
-
De-energize and lock out the machine per the Operators
Manual.
-
Gain access to the repair areas in the ends of the inverter
frame shown in dwg # 1034953. Block up the inverter frame such that
the weight of the inverter is taken off these joints and the joints
are in an unstressed condition.
-
Add new welds to the drive side of the inverter frame as
shown in dwg 1034953 sht 1.
-
Replace 6 bolts on the drive side inverter frame with the
longer bolts per dwg 1034953 sht 3. Alliance recommends that you
replace the bolts one at a time and apply the final torque when all
new bolts are installed.
-
Add 4 welded gussets to the operator side of the inverter
frame per dwg 1034953 sht 2.
-
Remove inverter blocking and restore the machine to the
operating configuration.
-
Remove lockouts and resume inverter operation. Check for
proper inverter rotation and operation.
-
Please advise Alliance when the preventative modification is
completed. Please contact Mr. Gary Kneale at
gkneale@alliancellc.net with your confirmation message.
Back to top
Back to Index |