Safety Bulletin

Bulletin number: SB100-02

Category: Maintenance

Date issued: October 17, 2002

Machine models: ASC/Pallmac Jumbo Prefeeders

Subject: Potential weldment defect

Back to Index
 
Description of Problem

Recommended Solution

Enclosures

 To our valued customer:

This service bulletin is part of an ongoing effort to provide quality service and support for all Alliance Machine Systems International, LLC products. If you need assistance or more information, please call Gary Kneale, Field Service Manager, at 509-535-0356 and select Option two.

Description of Problem

We have identified a potential problem with the pusher assembly on the ASC/Pallmac Prefeeder. There was an incident where a weld failed on the cross tube weldment, allowing the pusher assembly to drop down onto the lower conveyor.

Back to top

Recommended Solution

The weld on the pusher assembly should be inspected for visual cracks, paint chips, or signs of material deformation.  The weld should also be checked to ensure that it conforms with the weld symbols as indicated on the attached weldment drawing.  Any welds that are not to specification should be repaired to the drawing specification by a certified welder.

Back to top

Enclosures

This service bulletin is accompanied by the following documents:

  •  D12734 = Pusher support arm, right hand, pivoting

  •  D12735 = Pusher support arm, left hand, pivoting

Back to top

Back to Index